| Phase |
Activity |
Target Start date |
Target Completion date |
Actual date
achieved |
Comments |
Phase 1 - Healing Evening |
Set-up/start initial Healing Centre - one evening each week |
March 2005 |
March 2005 |
March 2004 |
Started 1 year earlier than planned |
| |
Phase 2 - Self
contained Healing Centre |
Raise funds to rent out property and pay for overheads |
Ongoing |
October 2006 |
- November
- 2006
|
May 2006 have raised the bulk of the funds required, but still
need some further funds to achieve target. |
| Find suitable property |
June 2006 |
December 2006 |
May 07 |
Suitable property not found -
larger Healing Rooms rented at The Rufus Centre from May 07 |
| Promote Healing Centre to therapists to rent rooms in
Healing Centre |
September 2006 |
October 2006 |
Nov 07 |
June 2006 looking to start to advertise for therapists |
| Set-up/start Healing Centre initially one evening per week |
December 2006 |
September 2008 |
|
Main object for 2006/7 is Phase II - hopefully complete by
the end of 2008 |
| Expand Healing Centre evenings from two or three evenings
per week |
October 2008 |
December 2008 |
|
Looking to expand Healing services to 2 or 3 evenings per
week |
| |
| Phase 3 - Purpose
built Holistic Healing Centre |
Establish with Architect area of site required |
November 2006 |
February 2007 |
Jan 07 |
Agree with Architect to size and nature of
site required |
| Produce Project Initiation
Document |
January 2007 |
March 2007 |
Mar 07 |
Produce document to initiate
project |
| Agree funding estimates for land the initial Healing Centre
(main building) |
June 2007 |
October 2007 |
Feb 07 |
Work closely with Architect on a realistic cost for land
and building |
| Find site and negotiate option to purchase
[subject to Planning Permission] |
July 2007 |
August 2008
|
|
Purchase option on land subject to Planning
Permission |
| Raise funds to purchase land |
January 2007 |
August 2008 |
|
Looking for land with a house already on the land to act as
initial Healing Centre |
| Obtain planning permission for Healing Centre |
September 2008 |
June 2008 |
|
As part of the purchasing the land, initial planning
permission will be sort in advance of purchase |
| Raise funds for building Healing Centre (main building) |
January 2008 |
June 2008 |
|
Not sure at the moment the funds required |
| Agree with Architect the final design of Healing Centre (main building) |
April 2008 |
November 2008 |
|
Final design agreement based on current/future models |
| Employ contractors to build Healing Centre (main building) |
September 2008 |
January 2009 |
|
Employ project manager and team of contractors |
| Start building Healing Centre (main building) |
January 2009 |
April 2009 |
|
Looking to complete initial building within 9 months (if
feasible) |
| Completion of Healing Centre (main building) |
October 2010 |
December 2010 |
|
Completion to include initial car parking facilities to
enable the opening of the Healing Centre |
| Opening of Healing Centre (main building) to the public |
January 2011 |
January 2011 |
|
Opening to the public |
| Agree funding estimates for out-buildings, landscape and
the rest of healing complex |
April 2010 |
October 2010 |
|
Work closely with Architect on a realistic cost for
out-buildings, landscape and the rest of healing complex |
| Raise funds for out-buildings, landscape and the rest of
healing complex |
January 2009 |
April 2009 |
|
Funding for the other areas of the Healing Centre complex |
| Architectural design of out-buildings, landscape and the
rest of healing complex |
October 2007 |
December 2008 |
|
Ongoing process over several years |
| Start building out-buildings, landscape and the rest of
healing complex |
September 2010 |
December 2011 |
|
Ongoing process over several years |
| Completion of project |
August 2012 |
August 2012 |
|
Ongoing process over several years |
| Phase |
Activity |
Target Start date |
Target Completion date |
Actual date
achieved |
Comments |