| Phases |
Activity |
Target Start date |
Target Completion date |
Actual date
achieved |
Comments |
Phase 1
Rented building |
Start Healing Centre |
2004 |
2004 |
2004 |
One evening/week at Flitwick, Bedfordshire. |
Phase 2
Rented Building |
Expanding Healing Centre |
2011 |
2012 |
|
Expanding healing centre from one evening/week to several evenings/days per week. |
Phase 3
Purpose built Healing Centre
|
Establish with Architect area of site required |
November 2006 |
February 2007 |
Jan 07 |
Agree with Architect to size and nature of
site required |
| Produce Project Plan |
January 2007 |
March 2007 |
Mar 07 |
Project initiation document |
| Produce Business Plan |
July 2008 |
September 2009 |
Dec 09 |
Business plan to show long term viability |
| Preliminary Cost Plan |
March 2011 |
June 2011 |
|
High level cost of Phase 2 - Healing Centre |
| Services Plan |
March 2011 |
August 2011 |
|
Cost plan of Solar Panels and other equipment to supply services to project |
| Pyramid Plan |
March 2011 |
August 2011 |
|
Cost plan of pyramid structure, including installation and delivery. |
| Agree funding estimates for land the initial Healing Centre
(main building) |
June 2007 |
June 2011 |
|
Work closely with Architect on a realistic cost for land
and building |
| Find site and negotiate option to purchase
[subject to Planning Permission] |
July 2007 |
July 2011 |
|
Purchase option on land subject to Planning
Permission |
| Raise funds to purchase land |
January 2009 |
July 2011 |
|
Looking for land with a house already on the land to act as
initial Healing Centre |
| Obtain planning permission for Healing Centre |
February 2010 |
August 2011 |
|
As part of the purchasing the land, initial planning
permission will be sort in advance of purchase |
| Raise funds for building Healing Centre (main building) |
May 2010 |
December 2011 |
|
Not sure at the moment the funds required |
| Agree with Architect the final design of Healing Centre (main building) |
December 2010 |
January 2011 |
|
Final design agreement based on current/future models |
| Employ contractors to build Healing Centre (main building) |
February 2011 |
February 2012 |
|
Employ project manager and team of contractors |
| Start building Healing Centre (main building) |
June 2011 |
March 2012 |
|
Looking to complete initial building within 9 months (if
feasible) |
| Completion of Healing Centre (main building) |
October 2012 |
December 2012 |
|
Completion to include initial car parking facilities to
enable the opening of the Healing Centre |
| Opening of Healing Centre (main building) to the public |
January 2013 |
January 2013 |
|
Opening to the public |
| Agree funding estimates for out-buildings, landscape and
the rest of healing complex |
April 2012 |
June 2012 |
|
Work closely with Architect on a realistic cost for
out-buildings, landscape and the rest of healing complex |
| Raise funds for out-buildings, landscape and the rest of
healing complex |
January 2012 |
April 2012 |
|
Funding for the other areas of the Healing Centre complex |
| Architectural design of out-buildings, landscape and the
rest of healing complex |
May 2012 |
December 2012 |
|
Ongoing process over several years |
| Start building out-buildings, landscape and the rest of
healing complex |
January 2013 |
December 2013 |
|
Ongoing process over several years |
| Completion of project |
August 2014 |
August 2014 |
|
Ongoing process over several years |
| |
Activity |
Target Start date |
Target Completion date |
Actual date
achieved |
Comments |